Framing

October 1st:
Framing began on Monday, September 25th. The crew worked for a total of 3 days this week.

1001Framing02.jpg
Lifting the beam into place

1001Framing03.jpg
At this time The Who was on the radio singing "I get my back into my living."

1001Framing04.jpg
Scott (the guy on the ladder) is about my size... but stronger.

1001Framing06.jpg
Nailing in the I-beam joists.

To learn more about the I-beam joists, click on the link below.

1001Framing08.jpg
Things you didn't want to know - how they unload materials.

1001Framing12.jpg
The subfloor is down.

October 5th:
Framing continued the week of October 2nd. The crew worked Monday and Tuesday at our place, then had to go to finish another job. Still, they made a lot of progress in just 2 days.

1005Framing03.JPG
Assemble the wall...

1005Framing04.JPG
... and hoist it into place.

1005Framing06.JPG
View of the work from Black Bear Trail.

1005Framing09.JPG
The end of framing, week 2.

1005Framing10.JPG
Another view of Bill & Sue's pond - this time from the master bedroom window.

October 11th:
Framing continued the week of October 9th.

1011Framing02.JPG
The subfloor was added to the loft.

1011Framing04.JPG
The first truss for the garage/mudroom goes into place.

1011Framing07.JPG
Installing the trusses takes a lot of strong backs.

1011Framing09.JPG
The crane made the job easier, and quicker. Let's hear it for hydraulic power.

1011Framing10.JPG
The rain held off, and the garage trusses are complete.

October 16th:
Framing - week 4.

1016Framing01.JPG
Setting the first rafters.

1016Framing02.JPG
The crew is happy that our home is relatively small - the rafters are only 20' long.

1016Framing06.JPG
Heave-ho!

1016Framing10.JPG
Our house reflected in Bill & Sue's pond.

1016Framing13.JPG
Setting the rafters - the crew makes quick and safe work of it nonetheless.

1016Framing15.JPG
October 16th - rafters and prow wall framing is complete.

1016Framing16.JPG
Mel celebrates the day's work and the view of Cabin Mountain from the loft.

1018Framing05.JPG
Dwayne & Zack position the center post.

1019Framing02.JPG
October 19th - end of week 4.

November 5th:
On October 23rd, Mel had surgery on her hand to repair some arthritis. After a brief trip back to Davis, we went to Winfield to visit with Mom. Emily came so we could celebrate her 23rd birthday. Then John went back to work for a week. So we were not around much for the past 2 weeks, and don't have many photos of the process.
 
But the framing crew did not just sit around waiting on us. Here are some pictures of their results.

1105Framing03.JPG
Details of the rafters and overhang on the prow.

1105Framing04.JPG
The sheathing and underlayment goes on for the roof.

1105Framing05.JPG
The windows arrived and are being installed.

The windows are Andersen 400 series casements.

1105Framing10.JPG
November 5th - end of week 6.

November 11th:
Framing weeks 7 and 8.

1126Framing02.JPG
The chimney is framed.

1111Framing01.JPG
Framing the screened porch.

1111Framing06.JPG
Mel and neighbors Dave (in blue) and Mason (in black) inspect the fireplace framing.

1111Framing07.JPG
The great room.

1111Framing08.JPG
The kitchen goes here. The screened porch is through the sliding door.

1111Framing10.JPG
Veteran's Day morning.