Inside Work

January 6th:
With the house "dryed in", work is beginning inside. We met with the builder and electrician on 2-Jan to go over the electrical plans. They wasted no time starting the electrical work. The breaker panel is installed, and wiring has started. The plumber should start soon.

0106Electric01.JPG
What happens when you flip this switch?

0106Electric02.JPG
Ta da! Light in the master bedroom.

0118Electrical01.JPG
The breaker box.

0118Electrical02.JPG
Wiring in the loft.

0118Electrical03.JPG
Installing electic in the insulated concrete forms requires a router.

January 18th update:
Electrical work continues inside the house. The plumber has the flu, so nothing to show there. Mel and John have spent the week shopping for faucets, tile, paint colors, kitchen appliances. There are some new photos below.

0118Kitchen01.JPG
Mel tries out the mock kitchen layout.

0118Bath01.JPG
Shopping for bathroom tile that works with our treasured soap dish.

January 19th update:
Today we visited Casselman Lumber in Grantsville MD to pick out kitchen and bath cabinets. It was too easy!! They had a perfect set of cabinets on display. A few personal touches and we were done. In one hour we picked out kitchen cabinets, 3 bath vanities, a linen closet, make-up vanity, and laundry cabinets. Photos of the kitchen are below.

0119Kitchen01.JPG
This was the display kitchen that caught our eye. It even has a cherry floor!

February 10th update:
The plumber and electician have been hard at it. There are 8 photos below.

0210Inside01.JPG
Malcolm is our plumber and HVAC man.

0210Inside02.JPG
What goes on behind the walls is a thing of beauty.

0210Inside03.JPG
Greg's clever communication to us. He got a reply the next day!

0210Inside04.JPG
Hot water flows thru the tubes and the fins radiate the heat to the great room floor.

0210Inside05.JPG
Fiberglass insulation under the tubes and fins reflect the heat up to the floor.

0210Inside06.JPG
The drywall waits to be installed. Next week? Maybe.

0210Inside08.JPG
Shhh! With this much sound insulation, the Master Bedroom should be quiet.

0210Inside07.JPG
We have been working on the lighting plan. There are a lot of choices!!

February 15th update:
This week the exterior walls were insulated, and they started drywalling. 4 new photos below.

0215Inside01.JPG
The blown-in cellulose insulation in the exterior walls fills the cavity completely.

0215Inside02.JPG
A close-up of the cellulose insulation in the loft.

0215Inside03.JPG
Drywall in the master bedroom.

0215Inside04.JPG
... and the hallway.

February 19th update:
Drywall work continues inside. It sure is dusty in there!!

0219Inside01.JPG
The dining area of the great room.

0219Inside02.JPG
The stairs to the loft, and the basement and master bedroom doorways.

0219Inside03.JPG
The kitchen.

0219Inside04.JPG
The drywall crew at work in the basement. Time to clean the camera lens!!

March 1st update:
Inside work is moving along quickly. The drywall is up, the mud is on, and all that dust is being cleaned up. Painting starts tomorrow.

0301Inside01.JPG
Jarrod sands the knotty pine for the great room ceiling.

0301Inside02.JPG
Hootie works on the wood ceiling.

0301Inside03.JPG
Mel, surrounded by drywall dust, admires the view.

0301Inside05.JPG
The joint compound has been applied, and sanded off onto the floor.

0301Inside06.JPG
The kitchen floor has been swept and mopped... once.

0301Inside07.JPG
Greg, our electrician, inspects the wiring for the under-cabinet lights.

March 3rd update:
The heat has been on for about a week now. We've wanted to post some photos of the boiler, but good photos are hard to get because all the work going on gets in the way. Here is a pretty good one though.

0310Inside10.JPG
The boiler and manifold for the in-floor heat.

March 4rd update:
The drywall primer was applied yesterday. The workers had a technique that made quick work of it. The colored paint will go on next week.

0304Inside01.JPG
Jarrod sprayed the primer on the walls...

0304Inside02.JPG
... and Greg used the super wide roller for a smooth finish!

March 10th update:
Lots of progress was made inside this week - fireplace installation, painting, and more. Enjoy the pictures below.

0310Inside01.JPG
Installing the zero clearance fireplace.

0310Inside02.JPG
The paint colors don't show so well in the photos... green in the mud room...

0310Inside03.JPG
... blue in the master suite and laundry...

0310Inside04.JPG
... and yellow in the kitchen, great room, and loft.

0310Inside05.JPG
Greg (The Wall) installed the switches and outlets.

0310Inside07.JPG
The doors, delivered from the finishing shop, await installation.

0310Inside08.JPG
Gary works on installing the great room ceiling...

0310Inside09.JPG
... which is going to be beautiful!

March 18th update:
There was lots of inside activity this week - tile floors were installed, the fireplace received its veneer of stone, the wood ceiling installation continued, and more...

0317Inside01.JPG
Greg gets his back into installing the doors.

0317Inside02.JPG
The closet doors in the master bedroom.

0317Inside03.JPG
The loft closet door.

0317Inside04.JPG
The cultured stone will be applied to the fireplace.

0317Inside05.JPG
Greg (a man of many talents) installs the stone.

0317Inside06.JPG
The (almost) finished product.

0317Inside07.JPG
Henry, the tile installer, put in a full week...

0317Inside08.JPG
The laundry room pantry has Glacier Bay Arctic Blue - off-white with blue highlights.

0317Inside09.JPG
The loft bathroom and closet have Corinth Flagstone - a reddish brown.

0317Inside10.JPG
Its Morro Bay Sage Green in the Master shower...

0317Inside11.JPG
... and the Master Bath floor.

0317Inside12.JPG
The Mudroom looks sharp with the green Continental Slate and maple wainscot from our own trees.

0317Inside13.JPG
The collar ties are wrapped, and the ceiling is nearly done.

March 25th update:
Work continued inside this week - doors, door and window casings, baseboards. Also Mel and John started work on the downstairs painting (ours to do). Plus, see Cherry Floors for a special treat!

0325Inside01.JPG
Jarrod and Curtis are doing most of the inside wood work, like the door casings in the Mud Room.

0325Inside03.JPG
The Laundry room shows the finished casings and baseboards.

0325Inside04.JPG
The munchkin doors lead to under-eave storage in the loft.

0325Inside02.JPG
Mel and John (and Emily) add some sweat equity to the family room.

April 1st update:
The Great Room/Loft ceiling was completed this week.

0401Inside01.JPG
Cellulose insulation is blown into the catherdral ceiling.

0401Inside02.JPG
Curtis nails the final pieces into the loft ceiling.

April 15th update:
The kitchen and bath cabinets were installed this week, along with the mantle.

0415Inside02.JPG
David Miller supplied the lovely hunk of cherry that became our mantle.

0415Inside03.JPG
The Master Bath vanity is natural soft maple to match the Master Bedroom flooring.

0415Inside04.JPG
The linen cabinet in the Master Bath.

0415Inside05.JPG
This is Mel's makeup vanity in the Master Bedroom.

0415Inside06.JPG
The Laundry Room vanity is stained blue to match the decor.

0415Inside07.JPG
The kitchen cabinets.

April 18th update:
Winter-like conditions have returned this week, which limits the work to inside work. Still progess is being made.

0418Inside01.JPG
The Laundry Room vanity gets its top. A small sink will finish it off.

0418Inside03.JPG
Door levers were installed.

0418Inside02.JPG
Recessed lights were installed. So was the spacesaver microwave.

April 21st update:
On Friday, the Corian Couple from Casselman installed the kitchen countertops.

0421Inside01.JPG
Mike and Jeannie install the last backsplash. They were almost done by the time we arrived.

0421Inside02.JPG
Jeannie buffs the island countertop with a Scotch Brite pad (maroon).

0422Inside01.JPG
The countertops really dress up the sage base cabinets.

0422Inside02.JPG
Mel likes the kitchen a lot! Jasmine thinks she is getting food.